This report sets out progress on Stage 3 of the project, including land assembly, contractor selection, site preparation and the securing of pre-lets and pre sales.
Councillor Mrs N.J. Bramhall, Executive Member for Property and Acquisitions, introduced the exempt information in relation to Marketfield Way, Redhill. During the discussion, a number of issues were considered in relation to land assembly, pre-lets, the selection of a main contractor, risk management, various stages of the project, projected scheme costs, other financial implications and the process for delegated decision making.
RESOLVED that the exempt information in relation to Marketfield Way, Redhill be noted.
Contact: Catherine Rose, Head of Corporate Policy Email: Catherine.Rose@reigate-banstead.gov.uk Tel: 01737 276766, John Reed, Head of Property Email: john.reed@reigate-banstead.gov.uk Tel: 01737 276571.
Publication date: 23/10/2018
Date of decision: 18/10/2018
Decided at meeting: 18/10/2018 - Executive