Decision details
Thames Water Deed of Easement for Marketfield Way
Decision Maker: Head of Place Delivery
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Decision:
On 23rd March 2017 Executive considered a
report regarding the redevelopment of the site known as Marketfield
Way, Redhill.
Executive agreed:
(ii) That the Head of Property be authorised to progress Stage 3 of
the Marketfield Way project, in accordance with the strategy set
out in the Executive report dated 26 February 2015 and updates set
out in this report, and bring forward the development, retaining
the commercial elements and selling or letting the individual
residential units on the open market at completion of the
development
(iii) That the Marketfield Way project be progressed in accordance
with the updated financial parameters set out in the exempt report
in Part 2 of this agenda, including further land assembly,
appointment of construction consultants, appointment of
construction building contractors, placement of contracts to move
statutory services on site, and conclusion of pre let
arrangements;
On 2nd July 2020 Commercial Ventures Executive Sub Committee
agreed:
That delegations previously authorised to the Head of Property in
all previous
reports to Executive, in relation to Marketfield Way, are now made
by the
Head of Place Delivery.
The Council is now required to enter into a deed of easement with
Thames Water relating to the building over/close to a public sewer
to facilitate the Marketfield development.
I being the Head of Place Delivery authorise entering into a deed
of easement with Thames Water relating to the building over/close
to a public sewer to facilitate the Marketfield
development.
Reasons for the decision:
To facilitate the development of Marketfield
Way.
Alternative options considered:
To not enter into the deed which will mean
that we will not be able to complete the development or in the
alternative have to divert the sewer resulting in substantial costs
and a delay in programme.
Contact: Peter Boarder, Head of Place Delivery Email: peter.boarder@reigate-banstead.gov.uk Tel: 01737 276201.
Publication date: 27/11/2020
Date of decision: 24/11/2020