Issue details

Agree a change of tenure mix and entering into a build contract for the Pitwood Park Development

In April 2018 the Executive approved the development of 25 houses and flats at Pitwood Park. Approval is now sought to vary the previously agreed tenure mix, the revised budgetary baseline position and to enter into a build contract with the recommended contractor.

Decision type: Key

Reason Key: Expenditure > £250,000;

Decision status: Recommendations Approved

Notice of proposed decision first published: 29/01/2020

Anticipated restriction: Part exempt  - View reasons

Explanation of anticipated restriction:
Not for publication by virtue of paragraph 3 of part 1 of schedule 12a of the Local Government Act 1972. The public interest in maintaining this exemption outweighs the public interest in disclosing the information.

Decision due: 27 Feb 2020 by Executive

Lead member: Portfolio Holder for Housing and Support

Lead director: Director of People

Contact: Penny Craig, Senior Development Manager Email: Penny.Craig@reigate-banstead.gov.uk Tel: 01737 276548.

Decisions

Agenda items

Documents

  • Agree a build contract and change of tenure mix for the Pitwood Park Development