The Executive Member for Property and Regeneration, Councillor Mrs N.J. Bramhall reported to the Executive on a significant opportunity for the Council to work in partnership with the private and public sectors to bring forward a scheme in the south of the Borough to provide employment opportunities in the area.
The report asked the Executive to consider entering into a Joint Venture (subject to oversight and conditions with suitable partners) to bring forward the development. As part of the joint initiative it was proposed that the Council would make a capital investment into the Joint Venture that would bring forward a Planning Application for the development (Planning Use Class B1 offices and associated uses) to support a leading business park. It was proposed that the Council would be an active participant in the project which if successful could provide significant social, economic and environmental benefits.
The Executive Member emphasised the complexity of the proposal and indicated that some of the key ingredients were currently confidential pending the completion of ongoing negotiations. This included the viability study; proposed heads of terms for a joint venture; financial and land ownership details; and details/terms for the potential Joint Venture Partners. These confidential documents were provided to the Executive in the Exempt part of its agenda.
The Executive were informed of the key stages to manage the project that included the initial viability; development of a site master plan; agreement with occupiers of the land; seeking planning permission (and associated consultation); obtaining construction tenders and construction of the development (which was likely to be phased).
RECOMMENDED that the Head of Finance be authorised to make the necessary amendment to the Council’s capital plan to fund stage 1 and stage 2 costs.
RESOLVED that:
(i) the Head of Property be authorised, in consultation with the Leader of the Council, Deputy Leader of the Council, Executive Member for Finance and Executive Member for Property and Regeneration to finalise and agree terms and enter into binding legal agreements with landowners to form Joint Venture Limited Liability Partnerships (LLP) or Companies (New Co) to bring forward for Planning and subsequently development the Employment land in Horley on the land as shown at Annex 1 to the Executive’s report, and subject to the key stage sign off set out in the Executive’s report;
(ii) the Chief Executive and Head of Property be appointed the Council’s representatives to the LLP/New Co, and in accordance with the delegations herein to give all necessary instructions to the LLP/New Co to progress development of the employment land, subject to key stage sign off set out in the Executive’s report;
(iii) the Head of Finance be authorised, in consultation with the Head of Property and the Leader of the Council, Deputy Leader of the Council, Executive Member for Finance and Executive Member for Property and Regeneration, to make the necessary arrangements to finance stage 1 and stage 2 costs, as set out in Annex 4 (in the Exempt part of the Executive’s agenda), through the Limited Liability Partnership or Company, subject to suitable security arrangements being made within the LLP/Company for the funding, and subject to the key stage sign off set out in the Executive’s report;
(iv) the Head of Finance be authorised to provide management accounting services to the Joint Venture vehicle and to make suitable arrangements for statutory accounting and reporting requirements;
(v) the Head of Property be authorised, as the Council appointed representative, in consultation with the Head of Finance, Leader of the Council, Deputy Leader of the Council, Executive Member for Finance and Executive Member for Property and Regeneration, to permit the LLP/New Co to make the necessary consultancy and contractor appointments to progress the project and submit a Planning Application, subject to the approved budget as set out in Annex 4 (in the Exempt part of the Executive’s agenda);
(vi) the Head of Property be authorised, as the Council’s representative to the property vehicle, in consultation with the Leader of the Council, Deputy Leader of the Council, Executive Member for Finance and Executive Member for Property and Regeneration, to instruct the LLP/New Co to enter into necessary agreements with the Council and other public sector organisations to bring forward development on the Horley Employment Land;
(vii) the Head of Property be authorised as the Council’s representative to the property vehicle, in consultation with the Leader of the Council, Deputy Leader of the Council, Executive Member for Finance and Executive Member for Property and Regeneration, to instruct the LLP/New Co to negotiate, agree and enter into Agreement for Leases and Leases with commercial organisations for pre lets subject to the key stage sign off set out in the Executive’s report;
(viii) the Head of Property be authorised, as the Council’s representative to the property vehicle, in consultation with the Leader of the Council, Deputy Leader of the Council, Executive Member for Finance and Executive Member for Property and Regeneration, to instruct the LLP/New Co to acquire land by Private Treaty. A list of site owners was set out at Annex 5 (in the Exempt part of the Executive’s agenda), and is subject to key stage sign off set out in the Executive’s report;
(ix) the Head of Property be authorised, as the Council’s representative to the property vehicle, in consultation with the Leader of the Council, Deputy Leader of the Council, Executive Member for Finance and Executive Member for Property and Regeneration, to authorise the LLP/New Co to enter into an indemnity with the Council with regard to CPO costs incurred in land assembly for the development of the Employment Land in Horley;
(x) the Head of Property be authorised, as the Council’s representative to the property vehicle, in consultation with the Leader of the Council, Deputy Leader of the Council, Executive Member for Finance and Executive Member for Property and Regeneration, to instruct the LLP/New Co to appoint the necessary Consultants and Contractors to prepare the necessary documentation to obtain competitive construction tenders, subject to key stage sign off set out in the Executive’s report; and
(xi) the Head of Property be authorised, as the Council’s representative to the property vehicle, in consultation with the Leader of the Council, Deputy Leader of the Council, Executive Member for Finance and Executive Member for Property and Regeneration, to instruct the LLP/New Co to agree and sign construction contracts subject to key stage sign off set out in the Executive’s report.
Reasons for decision:
To progress the Council’s Five Year Plan (2015-2020) that identified a number of objectives for the Council, including ‘to create new jobs for our residents’ benefit and to ensure there was a resilient, vibrant economy’. This would be achieved through a number of measures including promoting the Borough as a place to do business, securing resources to maintain and improve business related infrastructure, and working with partners and businesses to ensure that benefits of wider economic growth were enjoyed in the Borough.
In line with Policy CS5 of the Council’s adopted Core Strategy (2014) which confirms that the Council would promote and support continued sustainable economic prosperity and regeneration in the Borough. This would include planning for a range of types and sizes of employment premises to cater for the needs of established, growing and start-up businesses; and ensuring sufficient flexibility to meet their changing needs and attract new businesses.
Alternative options:
Do nothing and allow market forces alone to determine whether the land is developed in support of our local prosperity aspirations.
|